    Specification vs procurement: who is responsible for what?

    Who specifies, who buys and who carries design risk on UK interiors projects: prescriptive vs descriptive specifications, RIBA Stages 4–5 and a responsibility matrix.

    Faura · · 12 min read

    Kährs oak herringbone floor in a dining room with a timber table and chairs
    Oak herringbone floor in a dining room. Image: Kährs.

    The specification says exactly what is required: the products, materials, finishes, standards and workmanship. Procurement is the work of buying, ordering, tracking and delivering what the specification describes. On a UK project the designer or architect is normally responsible for the first, and whoever holds the purchasing contract for the second. The line blurs when a specification is written as a performance requirement rather than a named product, because design responsibility can then pass to the contractor or a specialist subcontractor.

    This guide sets out where each responsibility sits, how the RIBA stages shape it and how to keep the handover clean on a London interiors project.

    TL;DR

    • A specification defines the required quality, standard and materials. Procurement turns the approved specification into orders, deliveries and installed items.
    • With a prescriptive specification, design responsibility stays with the design team. With a descriptive one, it generally passes to the contractor or specialist.
    • The RIBA Plan of Work says what each stage achieves, not who does the work. Your appointments, contracts and a Responsibility Matrix settle that.
    • Most disputes come from changes made after approval. Write down who approves a substitution, a price rise or a lead-time change before anything is ordered.
    • Faura’s team handles procurement, logistics and delivery for approved trade accounts: one order, one invoice.

    Contents

    What a specification is, and what it is not

    NBS, the UK body that publishes specification systems for construction, describes a specification as the record of the specific requirements for work a client wants carried out: a detailed description of quality, standards, workmanship, materials and completion that evolves across a project. Architects, engineers and designers usually prepare it; it can be issued as a contract document read alongside drawings and models, and later feeds handover information.

    The International Code of the Specification describes the document set whose main purpose is to define the quality of materials and systems, the standard of workmanship and the construction processes. It lists its roles as a record of design decisions, a way to demonstrate compliance, a basis for estimating and tendering, a contractual document, an on-site working document, a tool for settling disputes and a project management tool.

    For an interior designer, that means a schedule of FF&E (furniture, fixtures and equipment) and finishes: manufacturer, reference, size, finish, quantity, and the standard it must meet, such as fire performance for upholstery or slip resistance for floors. Our guide to writing an FF&E specification walks through the fields that stop a schedule being misread.

    A specification tells the buyer what to buy. The quote, the order and the delivery plan come after it.

    What procurement covers

    Procurement starts when there is an approved specification to buy against. On an interiors scheme it typically includes:

    • selecting suppliers and confirming each item can be supplied as specified
    • costing, and getting written approval of items, materials and dates
    • placing orders and tracking manufacture
    • checking quality before dispatch
    • arranging logistics, delivery and installation
    • managing claims, warranties and snagging

    On larger projects the word has a second, contractual meaning: the procurement route is the way the building contract is let and the design team appointed, such as traditional procurement or design and build. Keep the two apart. The first is about buying products; the second is about who is contractually responsible for design and construction. Both affect who carries the risk if a specified item fails or arrives late.

    Our step-by-step FF&E procurement guide covers the buying process in detail. The rest of this article is about responsibility.

    Who is responsible for what

    The usual split on a UK interiors or fit-out project; your contract and appointment documents always override it.

    Task Usually led by Notes
    Developing the brief and design intent Designer or architect, with client Agreed before specification starts
    Outline specification Design team Used to align design and cost plan
    Final specification of products and finishes Design team (prescriptive) Contractor or specialist if descriptive
    Specialist subcontractor design Contractor or specialist Allocated to a defined stage
    Tender and supplier selection Depends on route: design team, client’s project manager or contractor Set by the procurement strategy
    Placing orders Whoever holds the purchasing contract Controls refunds, warranties and claims
    Delivery, installation and site programme Contractor, with suppliers Coordinated with the design team
    Approving samples and shop drawings Design team Before production starts
    Handover information and snagging Contractor and suppliers deliver; design team and client accept Starts before practical completion

    The third column matters most: the answer to “who is responsible?” is rarely one name. It depends on how the specification is written and which contract is in place.

    Prescriptive or descriptive: where design responsibility lands

    According to NBS, a prescriptive specification states exactly what products, materials and workmanship are required, and the design team keeps design responsibility. A descriptive specification states the required result and performance. For those items, design responsibility lies with the contractor and is likely to pass on to a specialist subcontractor. On a design-and-build contract it rests with the contractor regardless of who produced the design.

    A London example: you specify a named Italian oak veneer panel system with fixings and finish. That is prescriptive, and if the product does not suit the substrate, the design team owns the problem. If instead you write “joinery wall lining to achieve a stated acoustic and fire performance, finished in a natural oak veneer to approved sample”, that is descriptive. The joinery contractor or specialist designs the build-up and carries the design responsibility for it, usually backed by their professional indemnity insurance.

    Neither is better in every case. Prescriptive gives you control of what the client sees; descriptive suits complex systems where the specialist knows the technical detail. The RIBA Plan of Work 2020 Overview treats the interface between the design team and specialist subcontractors as a core project decision that should not be confused with choosing the procurement route. A traditional project can include performance-specified elements and a design-and-build project can have prescriptive ones, with many clients preferring the design team to specify products that are visible on completion.

    A practical rule for interior designers: any item the client will see and touch, such as the sofa, the pendant or the basin mixer, is usually worth specifying prescriptively. Items hidden in the construction are the natural candidates for descriptive wording.

    How the RIBA stages shape the split

    The RIBA Plan of Work 2020 organises UK projects into eight stages, from Stage 0 Strategic Definition to Stage 7 Use, and the British Institute of Interior Design explains how interior designers fit into those stages. Stage 6 is Handover. The stages help on interiors because specification and procurement sit in different ones.

    • Stages 2 and 3, concept and spatial coordination. NBS calls the outline specification a crucial design tool in these stages. It sets the quality level and lets the cost plan be tested before details are fixed.
    • Stage 4, technical design. The final specification is produced. The RIBA Overview says this stage needs input from the design team and specialist subcontractors whatever the procurement route, and recommends allocating specialist design work to Stage 4 rather than Stage 5 so the lead designer can programme all design work together.
    • Stage 5, manufacturing and construction. Most procurement happens here. According to the RIBA template published on the UK government’s Contracts Finder, Stages 4 and 5 overlap on most projects, and Stage 5 starts when the contractor takes possession of the site and ends at Practical Completion.
    • Stage 6, handover. It begins immediately after Practical Completion and finishes at the end of the Defects Liability Period.

    The Stage 4–5 overlap is where interiors teams get caught: long-lead items are ordered while other areas are still being specified, and if those items are not frozen, procurement starts on moving ground.

    The RIBA Overview also notes that the signing point depends on the route. On a traditional project the design team’s work should be substantially complete before the Building Contract is signed, with specialist subcontractor design completed after the contractor is appointed. On a two-stage design-and-build project the client may sign after major packages are secured. That tells you how much of your specification the contractor can still change.

    Use a Responsibility Matrix

    The RIBA Plan says what each stage achieves, not who does the work. That is set by appointments, contracts and the Responsibility Matrix.

    The RIBA Job Book says a Responsibility Matrix should identify, to a specific level of detail, who is responsible at each stage for the design of each building system. NBS adds that the matrix should be set up before the design stages and reviewed at the start of Stage 4, so it is clear who is producing the final construction information. It also points to the RIBA Plan of Work Toolbox, which includes templates for a Project Roles Table, a Responsibility Matrix and Multidisciplinary Schedules of Services.

    For an interiors job, build your own version with a row per package: loose furniture, lighting, joinery, sanitaryware, stone, soft finishes, ironmongery. For each, record who specifies, who approves samples, who orders, who receives and inspects deliveries, who installs and who owns the warranty. The same discipline helps after handover: contractor management and safety records are easier to keep when it is clear from the start who is responsible for each check and certificate.

    A sole designer with no contractor may hold more rows than expected. Check your terms of appointment so that purchasing, receiving and inspection are either written in or clearly excluded.

    From approved specification to delivered item

    Once a specification is approved, a sound sequence runs as follows, with where each step usually goes wrong:

    1. Confirm the specification is final. Each line should have a reference, finish, size, quantity and any standard it has to meet. Errors here are the most expensive, because they are copied into every order.
    2. Obtain a written quotation against the schedule. Compare it line by line with your specification so a substituted finish or dimension does not slip through.
    3. Get written approval before ordering. Every substitution, price increase or lead-time change needs sign-off from whoever is paying, before the order is placed.
    4. Approve samples and shop drawings. For made-to-order and bespoke items, the design team reviews and approves before production.
    5. Order and track. Someone has to own the chasing. Our guide to FF&E lead times and backward scheduling shows how to work back from the installation date.
    6. Arrange logistics and delivery. Access, storage, delivery windows and receipt checks need a named person on the day. Inspecting for damage at receipt, rather than at installation, keeps claims valid. For London sites, see our notes on FF&E logistics in London.
    7. Install, snag and hand over. Record defects, close them out, and collect warranties, care instructions and finish schedules.

    The party that buys controls the paperwork. Refunds, warranties, claims and delivery records follow the purchasing contract, so decide at the start whether that is you, the contractor or the client.

    Where responsibility goes wrong

    Three failure patterns recur.

    Vague wording that moves design risk. A specification that names a product category and finish but not the product leaves the supplier or contractor to choose. If the choice is wrong, the argument turns on whether it was descriptive or prescriptive, so say which it is.

    Changes after approval. The RIBA Overview warns about a related problem at the end of projects: teams focus on certifying Practical Completion at the expense of handover, and it recommends that handover activities start before the Practical Completion certificate is issued. The same discipline applies earlier: understand the cost and programme consequence of every change before an instruction is issued. Our piece on reducing late change orders explains how seeing products in person before the specification is frozen helps.

    No one owns the gap between Stage 4 and Stage 5. Specification is finished, orders are not yet placed, and the contractor has not arrived. Name an owner for that window.

    Where a trade showroom fits

    Specification is a decision made on information: samples, technical files, finishes, dimensions. A trade showroom puts that information in one place, and a procurement team behind it removes a layer of coordination.

    Faura is a trade-only interior design showroom and residency in Westminster, open by appointment Monday to Friday, 09:00 to 18:00. Across two floors of finished interiors, designers can specify from over 200 brands covering furniture, lighting, natural stone and surfaces, bathrooms and brassware, textiles, paint and architectural hardware, with samples, technical files and a materials library alongside. Designers can present schemes to their clients at the residency, and our team handles procurement, logistics and delivery: one order, one invoice.

    The specification you finalise with the product in front of you then goes to one team for ordering and delivery. Trade terms are agreed individually with each approved trade account. Interior designers can start with the residency and trade account. Architects and developers can see how specification support and FF&E procurement work, and the wider trade offer covers the product categories.

    Our view: specify with the product in front of you

    Most responsibility disputes in interiors begin when a specification is signed off from a catalogue page, a render or the memory of a showroom visit months ago. By the time of the order, nobody can say for sure what was meant.

    So we built Faura around specifying and buying in one place. A designer can handle a piece’s finish, scale and build quality, check its technical file and show the scheme to the client in the same building. A precise specification is the clearest way to keep design responsibility where the designer intends.

    Once approved, a specification should pass to procurement without being rewritten. Our team handles procurement, logistics and delivery, so the designer’s schedule becomes one order and one invoice rather than a series of supplier relationships to manage.

    The designer owns the design decisions; buying and delivery sit with a team set up for them.

    Faura Editorial

    FAQ

    Who is responsible for procurement on an interior design project?

    Whoever holds the purchasing contract is responsible for placing orders and holds the refund, warranty and claim rights. That may be the client, the contractor, or the designer if the appointment includes purchasing. The RIBA Plan is procurement-neutral, so the responsible party is set by your appointments and contracts, not by the stage.

    Does the designer or the contractor carry the risk if a specified product fails?

    It depends on how the item was specified. If the design team named the product, materials and workmanship (a prescriptive specification), design responsibility generally stays with the design team. If only the performance was described, it generally passes to the contractor or specialist. Confirm the position in your contract and with your professional indemnity insurer.

    Can specification and procurement overlap?

    Yes. Stages 4 and 5 overlap on most projects, so long-lead items are often ordered while other parts of the specification are still being finalised. Freeze the specification for each package before its order is placed, and record the date.

    What should a London designer record in a Responsibility Matrix?

    For each package, record who specifies, who approves samples and shop drawings, who orders, who receives and inspects deliveries, who installs and who holds the warranty. Add access and delivery arrangements for the site, since these often decide who is on hand to receive goods. Review it at the start of Stage 4.

    Can a trade showroom take on procurement for me?

    At Faura, yes: once you have specified from the showroom, our team handles procurement, logistics and delivery, with one order and one invoice. Visits are by appointment, and trade terms are agreed individually with each approved trade account. You can start at our trade access page.